The kitchens that finish on schedule are the ones planned before demolition. Cabinets are ordered and confirmed, the appliance list is final, and every trade knows their week before the first upper cabinet comes off the wall. Cabinet lead times are usually the longest item, which is why we lock them in first.
Week one is demolition and rough-in. The old kitchen comes out, and plumbing and electrical move to their new locations while the walls are open. If your town requires a permit and inspection for that work, this is when it happens.
Weeks two and three are walls, floors, and cabinets: drywall repairs, new flooring, and cabinet installation. Countertops are templated as soon as the base cabinets are set and level, and that template date is the most important moment in the whole schedule.
Weeks four and five bring counters, backsplash, appliances, and trim. The last day or two is reserved for the punch list: adjusting doors, touching up paint, and fixing the small things that make a kitchen feel finished rather than almost finished.